| Activity | Unit No. | Completion Date | Unit No. | Completion Date |
| First pour of concrete | 7 |
July-2011
| 8 |
Sep-2011
|
| Release calandria vault for end shield erection | 7 |
-
| 8 |
-
|
| Complete alignment & welding of end shield calandria and grout | 7 |
-
| 8 |
-
|
| Install calandria tubes | 7 |
-
| 8 |
-
|
| Complete coolant channel installation | 7 |
-
| 8 |
-
|
| Erection of feeders | 7 |
-
| 8 |
-
|
| PHT Hydro Test | 7 |
-
| 8 |
-
|
| Hot Conditioning of PHT System | 7 |
-
| 8 |
-
|
| Achieve criticality | 7 |
-
| 8 |
-
|
| Synchronisation | 7 |
-
| 8 |
-
|
| Commence commercial operation | 7 |
-
| 8 |
-
|