Location : Tarapur, Boisar, Dist. Thane, Maharashtra
Unit Reactor Type Capacity (MWe) Date of Commercial Operation Cumulative Generation Since
Commercial Operation (MUs)
TAPS Unit-1 BWR 160 October 28, 1969 49195
TAPS Unit-2 BWR 160 October 28, 1969 50702
TAPS Unit-3 PHWR 540 August 18, 2006 74626
TAPS Unit-4 PHWR 540 September 12, 2005 72037
Total 1400 - 246561

 

Generation Statistics during the Current Financial Year (FY 2025-26)
Unit Apr 2025 - Feb 2026 (FY 2025-26)
Gross Generation(MUs) Capacity Factor(%)
TAPS Unit-1 38  33
TAPS Unit-2 0 0
TAPS Unit-3 3240 75
TAPS Unit-4 3467 80

TAPS Unit-2 is under shutdown in project mode for ageing management / refurbishment.

 

Abbreviations:
BWR- Boiling Water Reactor
PHWR- Pressurised Heavy Water Reactor