Location : Kakrapar, Surat, Gujarat
Unit Reactor Type Capacity(MWe) Date of Commercial Operation
1 Pressurised Heavy Water Reactor(PHWR) 220 May 6, 1993
2 Pressurised Heavy Water Reactor(PHWR) 220 September 1, 1995
3 Pressurised Heavy Water Reactor(PHWR) 700 June 30, 2023
4 Pressurised Heavy Water Reactor(PHWR) 700 March 31, 2024



Cumulative Generation upto February-2025 (Since Commercial Operation)
Unit Cumulative Generation(MUs)
1 39300
2 40929
3 7770
4 4269

 

Generation Statistics during the Current Financial Year (2024-25)
Unit Gross Generation(MUs) Capacity Factor(%) Period
1 1512 86 Apr 2024 - Feb 2025
1 151 102 Feb 2025 - Feb 2025
2 1697 96 Apr 2024 - Feb 2025
2 122 83 Feb 2025 - Feb 2025
3 3838 68 Apr 2024 - Feb 2025
3 427 91 Feb 2025 - Feb 2025
4 4266 76 Apr 2024 - Feb 2025
4 436 93 Feb 2025 - Feb 2025

 

Previous Years Generation Statistics
Unit Year Gross Generation(MUs) Capacity Factor(%) Availability Factor(%)
1 2023-2024 1967 102 100
1 2022-2023 1793 93 91
1 2021-2022 1852 96 96
1 2020-2021 1817 94 96
1 2019-2020 1467 89 92
1 2018-2019 0 0 0
1 2017-2018 0 0 0
1 2016-2017 0 0 0
2 2023-2024 1708 88 87
2 2022-2023 1846 96 94
2 2021-2022 1652 86 84
2 2020-2021 1896 98 97
2 2019-2020 1962 102 100
2 2018-2019 1000 99 100
2 2017-2018 0 0 0
2 2016-2017 0 0 0
3 2023-2024 3932 85 91
4 2023-2024 3 17 51