Location : Kakrapar, Surat, Gujarat
Unit Reactor Type Capacity(MWe) Date of Commercial Operation
1 Pressurised Heavy Water Reactor(PHWR) 220 May 6, 1993
2 Pressurised Heavy Water Reactor(PHWR) 220 September 1, 1995
3 Pressurised Heavy Water Reactor(PHWR) 700 June 30, 2023
4 Pressurised Heavy Water Reactor(PHWR) 700 March 31, 2024



Cumulative Generation upto October-2024 (Since Commercial Operation)
Unit Cumulative Generation(MUs)
1 38661
2 40310
3 6465
4 2417

 

Generation Statistics during the Current Financial Year (2024-25)
Unit Gross Generation(MUs) Capacity Factor(%) Period
1 873 77 Apr 2024 - Oct 2024
1 164 100 Oct 2024 - Oct 2024
2 1078 95 Apr 2024 - Oct 2024
2 164 100 Oct 2024 - Oct 2024
3 2532 70 Apr 2024 - Oct 2024
3 0 0 Oct 2024 - Oct 2024
4 2414 67 Apr 2024 - Oct 2024
4 428 82 Oct 2024 - Oct 2024

 

Previous Years Generation Statistics
Unit Year Gross Generation(MUs) Capacity Factor(%) Availability Factor(%)
1 2023-2024 1967 102 100
1 2022-2023 1793 93 91
1 2021-2022 1852 96 96
1 2020-2021 1817 94 96
1 2019-2020 1467 89 92
1 2018-2019 0 0 0
1 2017-2018 0 0 0
1 2016-2017 0 0 0
2 2023-2024 1708 88 87
2 2022-2023 1846 96 94
2 2021-2022 1652 86 84
2 2020-2021 1896 98 97
2 2019-2020 1962 102 100
2 2018-2019 1000 99 100
2 2017-2018 0 0 0
2 2016-2017 0 0 0
3 2023-2024 3932 85 91
4 2023-2024 3 17 51