S.No. |
Activity |
Unit No. |
Completion Month |
Unit No. |
Completion Month |
01 |
First pour of concrete |
7 |
July-2011 |
8 |
Sep-2011 |
02 |
Release calandria vault for end shield erection |
7 |
Sep-2013 |
8 |
Mar-2015 |
03 |
Completed alignment & welding of end shield calandria and grout |
7 |
Dec-2015 |
8 |
Feb-2017 |
04 |
Installed calandria tubes |
7 |
July-2016 |
8 |
Preparatory activities are in progress |
05 |
Completed coolant channel installation |
7 |
Mar-2017 |
8 |
- |
06 |
Erection of feeders |
7 |
in progress |
8 |
- |